This is Hacker Public Radio Episode 4583, for 2026-02-25
|
||||
Today's show is entitled, "Nuclear Reactor Technology - Ep 7 Small Modular Reactors"
|
||||
The host is Whiskeyjack and the duration is 00:13:42
|
||||
The flag is Clean, and the license is CC-BY-SA
|
||||
The summary is "This episode covers Small Modular Reactors, or SMRs."
|
||||
This episode is the 7th and 8th part series on nuclear reactor technology.
|
||||
In this episode, we will describe a topic which has been in the news in recent years,
|
||||
which is small modular reactors or SMRs for short.
|
||||
What is an SMR?
|
||||
Basic definition.
|
||||
A small modular reactor is a nuclear reactor that is designed to be largely built
|
||||
in a factory and subject to as little on-site assembly as possible.
|
||||
The main goal is to lower costs by reducing construction times and allowing a more
|
||||
rapid start of return on investment.
|
||||
Size-based definition.
|
||||
Some people put a numerical size limit on SMRs, saying there must be no larger than 300
|
||||
megawatts to qualify as an SMR.
|
||||
However, this limit is not universally accepted and not all SMR designs fall within this
|
||||
arbitrary limit.
|
||||
I will ignore this numerical limit and just consider anything to be an SMR if it meets
|
||||
the criteria of being largely built in a factory with minimal on-site assembly.
|
||||
The actual goal of the SMR idea.
|
||||
The actual goal of the SMR idea is to build reactors rapidly and efficiently on more
|
||||
less than a assembly line basis, rather than can crafting each one.
|
||||
One engineer in the nuclear industry has compared building reactors to building ships.
|
||||
Traditional shipbuilding techniques involve assembling each ship from the keel up on the slipways
|
||||
from individual components.
|
||||
Newer shipbuilding techniques assemble ships as separate blocks inside factory-like
|
||||
buildings and then join completed blocks together in a final assembly stage.
|
||||
This requires careful planning and tight-quality control, but results in building ships
|
||||
much more rapidly and economically.
|
||||
This engineer said that SMRs are attempting to build this doorway of doing things to the
|
||||
nuclear reactor industry as well.
|
||||
SMR categories, small versus micro.
|
||||
One very important distinction that needs to be made but seldom is happens to be the
|
||||
difference between size ranges.
|
||||
These different size ranges are often meant to meet different use cases which in turn
|
||||
has further influence on their designs.
|
||||
Small SMRs SMRs in the several hundred megawatt range are meant for normal grid-scale
|
||||
utility usage.
|
||||
These designs are often based on well-proven design, scale down and simplified and use
|
||||
normal commercial fuel.
|
||||
These small SMRs typically come from companies with long experience in the nuclear
|
||||
industry.
|
||||
Small SMRs and small grids.
|
||||
In addition to normal utility use, these small SMRs are particularly attractive to small grids
|
||||
where absorbing a large power plant into the grid is difficult.
|
||||
Adding a large amount of capacity all at once that may be a significant fraction of their
|
||||
entire total is difficult from an operational and economic standpoint.
|
||||
Some of these utilities may have built nuclear power plants decades ago when reactors
|
||||
were much smaller and are finding that newer ones are much larger.
|
||||
The attraction of SMRs to them is the smaller size.
|
||||
Checker wet SMRs from micro loads.
|
||||
Designs in the tens of megawatts are often meant for special use cases, although some vendors
|
||||
do promote them as alternatives to normal full-scale utility plants.
|
||||
These use cases can include such things as powering communities in remote areas which are
|
||||
far from normal utility grids.
|
||||
These places are usually powered by diesel generators which are very expensive to operate due
|
||||
to the cost of shipping and fuel.
|
||||
As well as the higher cost of diesel compared to normal utility power, these communities
|
||||
often have no normal roads connecting them to the outside world and after bringing the
|
||||
diesel once per year by ship, winter ice roads or in the worst case by air.
|
||||
This is exorbitantly expensive but numerous attempts to replace diesel by other means haven't
|
||||
held now rarely been successful.
|
||||
Yet another use case is a related one of providing electric power to mines in remote areas.
|
||||
These face the same problems as remote communities.
|
||||
Micro SMRs for large industry.
|
||||
In some cases however, the intent is to provide a process heat for large industrial applications
|
||||
such as a production of chemicals.
|
||||
In these cases, the micro SMRs would be replacing natural gas or coal.
|
||||
The SMRs in these cases are often designed to produce heat at higher temperatures than
|
||||
typical utility reactors.
|
||||
As can result in very different designs such as high temperature gas-cooled reactors.
|
||||
SMRs to power data centers.
|
||||
Some parts of the AI industry are talking about using SMRs to power their data centers.
|
||||
However, I suspect that this will be forgotten once the AI bubble pops which could happen
|
||||
in the near future, possibly even before this podcast airs.
|
||||
As such, I will ignore this use case.
|
||||
Let's just nonsense about micro small modular reactors, you say.
|
||||
Unfortunately, the terminology used today originates from period when ideas were not well-defined.
|
||||
Furthermore, ideas that were around before the SMI term earthquake have been rebranded
|
||||
as SMRs for marketing reasons.
|
||||
The result today is that some very different things are being called SMRs and different
|
||||
people are using different terms to just try to distinguish between them.
|
||||
Some people are using the term micro SMRs, while others are calling them MMRs or micro
|
||||
modular reactors.
|
||||
I will simply call the very small ones micro SMRs for simplicity.
|
||||
Small reactors as modular reactors that are not SMRs.
|
||||
Not every small commercial power reactor is an SMR.
|
||||
The larger SMRs are more or less in the same size range as reactors built in the 1960s.
|
||||
However, these were not designed with the sort of modular construction techniques that
|
||||
are one of the defining features of an SMR.
|
||||
India was still completing 200 megawatt reactors in the early 2010s before switching to larger
|
||||
sizes.
|
||||
These were well within the SMR size range but not considered to be SMRs.
|
||||
Conversely, one builder of large tube type heavy water reactors which inherently have modular
|
||||
features has taken experience from building reactors in Asia and applied it to their
|
||||
newest 1000 megawatt design.
|
||||
This incorporates modular design and rapid assembly techniques in order to build a reactor
|
||||
more quickly, but as these are large reactors, they are also not SMRs even if they are
|
||||
modular.
|
||||
Standard versus proprietary fuel.
|
||||
SMRs which are based on scaled down conventional designs normally used standard commercial
|
||||
fuel.
|
||||
This is typically uranium oxide fuel enriched between 3 and 5%.
|
||||
Some SMRs, particularly the micro SMR ones, use a proprietary fuel, often with higher
|
||||
enrichment levels.
|
||||
These proprietary fuels are often enriched to just below 20% uranium to 35.
|
||||
If you recall from a previous episode in this series, uranium which is enriched to 20%
|
||||
or higher is considered to be military material and cannot be used in civilian applications
|
||||
aside from a few research reactors.
|
||||
As a result of this, there are currently no commercial suppliers for this great a fuel
|
||||
outside of small amounts that are made in Russia and very limited experimental amounts
|
||||
that are made in the US from diluted surplus weapons stockpiles.
|
||||
While some of the SMR vendors claim to have fuel suppliers lined up, this fuel is not
|
||||
in production from reliable sources and so buyers face additional risks in using these reactors.
|
||||
There is no such risk when it comes to SMRs which you standard commercial fuel.
|
||||
Wear SMRs are currently being built.
|
||||
There are many different proposals for SMR designs, but I will just focus on ones that
|
||||
are actually built under construction or have signed utility customers and will almost
|
||||
certainly be built.
|
||||
HDR-PM in China.
|
||||
This is an SMR that often gets mentioned as it is seen as the first to actually go into
|
||||
operation.
|
||||
This reactor was mentioned in a previous episode in this series.
|
||||
It is a high temperature gas cooled, pebble bed reactor.
|
||||
The basic design is descended from reactors built in Germany starting in the 1960s.
|
||||
A Chinese research group bought the design information from Germany and continued to work
|
||||
on it further.
|
||||
The fuel is contained together with graphite moderator in billiard ball size spheres which
|
||||
are in bins.
|
||||
The fuel is uranium enriched to 8.5% to coolant is helium gas.
|
||||
Two reactors jointly feed a single 210 megawatts steam turbine generator.
|
||||
The reactor went into operation delivering power to the grid at the end of 2021.
|
||||
Repurposed ship reactors in Russia.
|
||||
Several different models of reactors originally designed for powering ships have been used
|
||||
to provide power for remote Arctic communities in Russia.
|
||||
These are pressurized water reactors using uranium enriched to under 20%.
|
||||
They have been mounted on barges and on land.
|
||||
They are used to replace diesel or small coal plants.
|
||||
Some people like to cite these as the first SMRs.
|
||||
However, as repurposed marine reactors, it is questionable whether these are true SMRs,
|
||||
but that is a matter of semantics.
|
||||
They are, however, a good example of how micro SMRs can be used to provide power to remote
|
||||
towns and mines.
|
||||
300 megawatt BWR in Canada.
|
||||
Canada is building a power plant just use of Toronto that has 4 300 megawatt boiling water
|
||||
SMRs for a total of 1,200 megawatts.
|
||||
These are scaled down and simplified conventional reactor designs using standard commercial
|
||||
fuel.
|
||||
The production started at late 2024 and the first reactor is expected to go into commercial
|
||||
operation in 2029.
|
||||
Recent news suggests that the province of Ontario may go back to building larger reactors
|
||||
after this plant is built.
|
||||
But several smaller provinces are interested in this SMR, due to its small size, soothing
|
||||
their small electricity grids.
|
||||
470 megawatt PWR in the UK.
|
||||
The UK has announced plans to build a series of 470 megawatt, pressurized water reactors
|
||||
from a UK company.
|
||||
These are scaled down and simplified conventional reactor designs using standard commercial
|
||||
fuel.
|
||||
The reactors are designed to be transported to this site in modules and assembled there,
|
||||
but with most of the work being done in the factory.
|
||||
At 470 megawatt, these are notably larger than the 300 megawatt cutoff used by some people,
|
||||
but as the ultimate goal is modularity, if they can meet that intent, I think they can
|
||||
recently be called SMRs.
|
||||
Construction has not yet started, but as plans are well advanced, they are probably worth
|
||||
mentioning.
|
||||
25 megawatt PWR in Argentina.
|
||||
This is often cited in sub-articles as one of the first commercial SMRs, but is actually
|
||||
a scaled down prototype for an SMR that is intended to be four times the size.
|
||||
This is a scaled down pressurized water reactor.
|
||||
Construction has been on again off again due to financial and economic problems in Argentina,
|
||||
so it's hard to say when or if this will ever be completed.
|
||||
I thought it was worth describing here though, because it is mentioned in a number of news
|
||||
articles on SMRs.
|
||||
Various experimental SMRs.
|
||||
There are numerous experimental SMRs on the drawing board or under test.
|
||||
Some may be built as prototypes.
|
||||
This, however, will probably never be built or, if built, go beyond the prototype stage.
|
||||
Modular large reactors, newer large reactors are starting to incorporate modularity into
|
||||
their designs as well.
|
||||
These are composed of large modules weighing from 100 to 1000 tons.
|
||||
The amount of concrete and steel required in construction has also been drastically reduced.
|
||||
There can be large economies of scale in electric power generation.
|
||||
As larger reactors incorporate modular construction, and as SMRs get larger, the advantages
|
||||
of SMRs in grid scale utility applications may fade away except for smaller grids.
|
||||
Conclusion, SMRs are a new trend in nuclear reactor design.
|
||||
However, there are really two different things which fill two different needs.
|
||||
One style is intended to adopt designs which allow for more rapid construction with
|
||||
more of the work being done in the factory and less on the construction site with the overall
|
||||
goal of reducing costs.
|
||||
The other style is to provide very small reactors to power remote communities and minds
|
||||
or to provide process heat to large industries.
|
||||
The first SMRs are in operation or under construction.
|
||||
The most promising grid scale designs that present are simply scaled down and simplified
|
||||
conventional designs that use standard commercial fuel.
|
||||
larger reactors will incorporate modular construction techniques, blurring the lines
|
||||
between them and SMRs.
|
||||
In the next episode, we will talk about future reactor technologies, particularly what
|
||||
are referred to as generation 4 reactors.
|
||||
This concludes the seventh episode of an eight-part series on nuclear reactor technology.
|
||||
You have been listening to Hacker Public Radio at Hacker Public Radio.org.
|
||||
Today's show was contributed by a HPR listener like yourself.
|
||||
If you ever thought of recording podcast, click on our upload link
|
||||
to find out how easy it is.
|
||||
Hosting for HPR has been kindly provided by an AnHonestHost.com, the Internet Archive,
|
||||
rsync.net, and our mirror network.
|
||||
Unless otherwise stated, today's show is released under a Creative Commons
|
||||
Attribution-ShareAlike 4.0 International (CC BY-SA 4.0) license.
|
||||
Reference in New Issue
Block a user